Navi Mumbai Metro Phase 2: approved, and not started yet

Written by Raj Rawthar
Last updated 4 Nov 2026 · 13 min read

In short

  • Eleven stations run today, 11.1 km from CBD Belapur to Pendhar, open since 17 November 2023. Four carry Kharghar's name, Pethali and Pendhar sit at Taloja's edge, and nothing has been added since.
  • The state cleared ₹5,575 crore in June 2026 for the Taloja to Khandeshwar corridor. Its own note puts work from FY 2027-28 and full running at FY 2031-32.
  • Only soil testing is contracted and the design consultant's tender shows as cancelled. So Phase 2 is approved, not coming.
  • Two more lines aim at Taloja from the Kalyan side. Line 12 has been building since March 2020, due May 2028 at Amandoot, by a December 2025 report. Metro 12A, 18.40 km and twelve stations, was approved on 27 October 2026 with no builder hired.
  • The rule: if the flat only works once Phase 2 runs, it doesn't work. Pay the price you'd pay with no new station at all.
In this post
  1. Eleven stations are running, and four of them say Kharghar
  2. What the state approved in June, and what it will cost
  3. Nobody has confirmed a train in Taloja yet
  4. Two more lines aim at Taloja, both from the Kalyan side
  5. What this does to your Taloja or Kharghar budget

Your broker kept saying the word metro on Sunday. Then he said Phase 2, and the price suddenly made sense to everyone in the room except you.

That’s the part that keeps you up. The Taloja flat is about a third of the Kharghar one. Is the train the reason for that gap, or is the train just being used to sell you a flat?

I won’t pick your flat. I’ll tell you which stations you can ride this Sunday, which ones live only on paper, and what each should do to your budget.

Here’s the short answer. Nothing new is running. The metro that exists goes from CBD Belapur to Pendhar, and it opened three years ago.

Two Taloja lines now have the state’s approval, and neither has a builder on site. On the state’s own targets, the trains are years away.

So pay for the station you can walk to this Sunday, and not for the one drawn on a plan.

Eleven stations are running, and four of them say Kharghar

You can ride this metro today. It runs 11.1 km from CBD Belapur to Pendhar, with eleven stations, open since 17 November 2023. That’s the whole network, and we read Wikipedia’s page on Line 1 on 28 October 2026.

Stations you can ride11CBD Belapur to Pendhar
Length of the line11.1 kmAll of it on pillars
Stations added since it openedNoneOpened 17 Nov 2023

Find your nearest station here. If it isn’t on the list, you can’t ride it today.

In order from CBD BelapurStationRunning since 17 Nov 2023?
1CBD BelapurYes
2R.B.I. ColonyYes
3BelpadaYes
4Utsav Chowk, KhargharYes
5Kendriya ViharYes
6Kharghar VillageYes
7Central Park, KhargharYes
8Pethpada, KhargharYes
9AmandootYes
10Pethali, TalojaYes
11PendharYes

Four of those names carry Kharghar. The last two, Pethali and Pendhar, sit at the Taloja end. So Kharghar is already a metro node, and Taloja only touches the line at its tail. That’s a difference you can walk.

Now the honest limit, where people usually get it wrong. It doesn’t take you to Vashi, or to town. It ends at CBD Belapur, beside the old railway station, and feeds you to the train that does the long haul.

Does your office sit on this line, or well past it? Answer that before you pay extra for a station.

These four numbers decide whether you’d really use it.

Fare, end to end₹30₹10 for a short hop
The whole run25 min 30 secPendhar to CBD Belapur
Wait at peak10 min15 off-peak, Nov 2025
Service hours6 am to 10 pmRoughly, every day

By its second birthday, in November 2025, it had carried 1.15 crore trips, says the Free Press Journal’s two-year report. Metro Rail News separately counts over 12,000 riders a day.

That run time has been the timetable since 13 July 2026, when CIDCO, the state body that planned and built Navi Mumbai, trimmed ninety seconds off the run.

So picture a Tuesday from the Taloja end. Auto to Pendhar, wait up to ten minutes, ride 25 minutes, then cross to the railway platform next door.

Count your own walk at both ends, because that’s what every route map leaves out. The last train goes at about ten, so a late meeting means a cab home.

And here’s what I can’t put a number on: how long the water runs, and how well lit the walk from station to gate is at nine at night. Go once after dark and ask a resident both. A station two kilometres away won’t fix a dark lane or a dry tap.

What the state approved in June, and what it will cost

On 12 June 2026 the state cabinet cleared ₹5,575 crore for two more pieces of this metro. That’s the news your broker was paraphrasing.

One piece is small: 3.02 km and two stations, from CBD Belapur to Sagar Sangam. The other is the one Taloja cares about.

It starts in the Taloja industrial belt, near Pendhar but not yet joined to it, then runs through Kalamboli and Kamothe to Khandeshwar and the new airport. Mumbai Live’s report names its eight stops.

Not one of them exists yet: two at MIDC Taloja, Kalamboli Kasadi, Sector 13 and Sector 7E Kalamboli, Sector 2E and Sector 10 Kamothe, and Khandeshwar.

Here’s the timeline, with every date tied to a report.

  1. 2011 CIDCO first proposes a metro line through Taloja.
  2. Nov 2023 The first stretch opens, CBD Belapur to Pendhar.
  3. Dec 2025 The new airport takes its first paying flights nearby.
  4. Jun 2026 The cabinet clears the money for the Taloja line.
  5. Oct 2026 The state clears Metro 12A, a second line in from the Kalyan side.
  6. FY 2027-28 Work is expected to begin, says the state’s own note. FY is the state’s money year, April to March.
  7. FY 2031-32 Full running is the target. Nobody has promised it.

Those last two lines are from the Free Press Journal’s report on the cabinet decision. They’re a target, not a promise, and I’d read them as the earliest case.

Nobody has confirmed a train in Taloja yet

Approved and coming are not the same thing. Four things are still open, and each matters to you.

  • No builder. The Metro Rail Guy’s tender list shows one soil-testing contract awarded and the design consultant’s tender cancelled. Nobody has been hired to build it.
  • A gap in the middle. The approved stretch runs Khandeshwar to the Taloja industrial belt. The short link from there back to Pendhar still needs clearance of its own, and the reports put it at anywhere from 2.2 km to 3.87 km.
  • A long run-up. The plan dates from 2011, when it was costed at ₹1,605 crore. The ₹5,575 crore cleared this June covers it and the Belapur to Sagar Sangam stretch together, so the two figures aren’t like for like. Fifteen years to reach approval warns you about the building time, not just the price.
  • No firm map. One report gives the corridor 8.15 km with eight stations. Another gives 14.07 km with eleven. We can’t show you a map we’d trust.

So treat Phase 2 the way you’d treat a raise your boss has agreed to but hasn’t dated. Good news. No reason to borrow more this month.

Two more lines aim at Taloja, both from the Kalyan side

Here’s the part nobody tells Taloja buyers. The metro work actually moving towards Taloja starts in Kalyan, not Belapur. Four things get called the Taloja metro; only one sells tickets.

What people call itWhere it stands today
Navi Mumbai Metro Line 1Running since 17 November 2023. Eleven stations
Phase 2, or Line 2, Taloja to KhandeshwarApproved June 2026. No builder. Work targeted FY 2027-28
Mumbai Metro Line 12, Kalyan to AmandootBeing built since March 2020. Target moved to May 2028
Metro 12A, Manpada-Katai Naka to TalojaApproved 27 October 2026. No builder, no pillars

Line 12 is the one with pillars going up. Wikipedia’s page on it gives 22.17 km and 18 stations, from Kalyan railway station to Amandoot, built since March 2020.

Amandoot is the bit worth noticing. Look back at the first table: it’s station nine, and you can ride it today.

The newer one is Metro 12A, cleared on 27 October 2026. The Free Press Journal’s report gives its shape.

Length of Metro 12A18.40 kmAll of it elevated
Stations you could rideNone of 12Nothing built yet
Approved cost₹13,856 crRailway plus the roads beside it

It runs from Manpada-Katai Naka to Taloja via Kalyan Phata, and Metro Rail News has it joining Line 12 near Khutari village to finish at Amandoot. So it widens the Kalyan door rather than opening a new one.

The Chief Minister asked for it in three and a half years. Hold that against Line 12: six and a half years of building so far, and still no opening.

Approved is the cheapest word in this business. Only the first row above sells you a ticket.

Does your family travel towards Kalyan and Dombivli more than Belapur? Then these two lines matter more than Phase 2 ever will.

What this does to your Taloja or Kharghar budget

Here’s the number the route-map pages never print. It’s from our own list of homes, read on 28 October 2026.

Middle starting price on our own list, in lakh rupees
Taloja36 lakh
Kharghar1.02 crore

That middle figure is the halfway project’s cheapest home, out of the 63 Taloja homes we list and the 78 in Kharghar. New buildings only, so resale flats aren’t in it.

Now don’t read the train into that whole gap. Kharghar is the older, more finished node, and its schools and hospitals are standing rather than drawn. The running line is one reason among several, and nobody can honestly tell you how much of the gap it owns.

Put three real homes beside each other, with the handover month each has given MahaRERA, the state’s own register of approved projects.

HomeStarts atUp toHandover due
Mahaavir Exotique, Kharghar₹47 lakh₹87 lakhDec 2026 and Dec 2027, in two parts
Sai Shri Narayana, Taloja₹25.28 lakh₹36.56 lakhDec 2027
Millennial Towers, Taloja₹41 lakh₹68 lakhDec 2029

Mahaavir Exotique is registered in two parts, so ask which part your flat sits in.

Hold those dates together. You’d have your keys, and your child in a Taloja school, years before the first train is even targeted.

So the years that decide whether you like living there have no metro in them. Can the place hold you that long? Judge it on that.

The objection I’d raise myself

Get in now, before Phase 2 is priced in. That’s the argument, and it isn’t a silly one. Here’s where I think it’s weak.

  • The running line is small. Over 12,000 riders a day is a busy bus route, not a city-changing force.
  • It still ends inside Navi Mumbai. The airport opened to paying flights in December 2025, and its metro link is approved, not running.
  • Count the years out loud. FY 2031-32 is four or five years of EMI away, and an EMI is the fixed sum you pay the bank each month.

Buy under construction and you pay that EMI and your rent together until the keys come. From today that overlap is roughly 14 months at Sai Shri Narayana and just over three years at Millennial Towers. Put your own numbers into the EMI calculator on this page.

My honest answer is this. If the asking price already assumes the train, your early-buyer advantage has gone to the seller. If it doesn’t assume the train, you lose nothing by ignoring it. Either way, the metro shouldn’t move your number.

Four checks before you pay extra for a metro

These four take one Sunday morning, and none of them needs an agent.

  1. Walk it Stand at the building gate. Walk to the nearest station on the table above, at the hour you’d really leave. Time it on your phone.
  2. Name it Ask the agent to name the station, then find it in the first table. If it isn’t there, it isn’t a station yet.
  3. Check the register Look the project up on MahaRERA and read its handover month there.
  4. Ask in writing Ask for the metro claim in the agreement. Nobody will put it there. That tells you what the claim is worth.

Who should buy near the running line, and who shouldn’t bother

Four kinds of family ask us this, and the metro means something different to each one.

If this is youWhat the metro actually meansWhere I’d look first
One of you takes a train to Belapur or beyond each morningA lot. A running station inside your walk is worth real moneyKharghar, by one of its four stations
Your budget stops under fifty lakhLittle, in practice. Only a rare Kharghar project starts that lowTaloja, judged on price and daily life
You need the keys inside three yearsNothing. No new station arrives that soonEither node, sorted by handover month
You drive, or you work from homeLittle. The road stays the same width either wayTaloja, with the saving spent on space

Found your row and felt relieved? That’s your answer. Buy the flat for its price and its homes, not its train.

One honest limit. This post doesn’t cover resale or rental yield in either node, because we don’t hold figures we’d trust enough to print.

What to watch, and the rule I’d carry

Three things would turn Phase 2 from a plan into a train. Two more decide the Kalyan side.

  • A named contractor and a work order for the Khandeshwar to Taloja stretch.
  • Clearance for the 2.2 to 3.87 km link between Pendhar and the industrial belt.
  • Pillars going up. You’ll see those from the road.
  • Line 12 from Kalyan reaching Amandoot. That one is already being built.
  • A named contractor for Metro 12A. Without one, that three-and-a-half-year deadline is a wish.

We’ll watch all five and update this page when one lands. Until then, it’s a line on a plan.

So the rule is simple. If the flat only works once Phase 2 runs, it doesn’t work. Pay the price you’d pay with no new station at all.

It costs you nothing if the train arrives early, and saves you a great deal if it never does.

Come and do the station walk with us on a Sunday instead of reading another route map. The advisor’s name sits on every project page, and we’ll tell you straight when the metro won’t help you at all.

Buying your first home here? Our six steps to buying a flat in Navi Mumbai put this in order, from the loan to the keys.

Questions buyers ask

Is the Navi Mumbai Metro running today?

Yes. One line runs 11.1 km from CBD Belapur to Pendhar, with eleven stations, open since 17 November 2023. No station has been added since.

Does the metro reach Taloja?

It reaches the edge of it. The last two stops, Pethali and Pendhar, sit at the Taloja end. The industrial belt and the sectors beyond have no station running.

When will Navi Mumbai Metro Phase 2 open?

No date is confirmed. The state cleared the money in June 2026, and its note puts the start of work in FY 2027-28 and full running in FY 2031-32. No contractor has been reported, so treat those as targets.

Is any metro actually being built to Taloja?

Yes, but not the one people mean. Mumbai Metro Line 12 runs from Kalyan to Amandoot, at Taloja’s edge, and has been under construction since March 2020. Its target was December 2027; a December 2025 report put completion at May 2028. It connects Taloja to Kalyan and Dombivli, not to Belapur.

What is Metro 12A, and does it reach Taloja?

It’s a new line the state approved on 27 October 2026: 18.40 km and twelve stations from Manpada-Katai Naka to Taloja via Kalyan Phata, costed at ₹13,856.37 crore. It joins Line 12 and ends at Amandoot. No builder has been named, so treat the three-and-a-half-year deadline as a target.

Does the metro go to the new airport?

Not yet. The airport took its first paying flights in December 2025. The metro link to it is part of what the state approved in June 2026, and it isn’t built.

Should I pay more for a flat near a planned station?

No. Pay for what’s running. A planned station is a bonus you may collect in five years or may not collect at all, and you’d be paying for it with interest every month until then.

Homes in Taloja

See all homes in Taloja

Ask Raj about Taloja

A shortlist that fits your budget and date, on WhatsApp. No calls unless you ask.

Add email

WhatsApp first, one call · Number never sold · Privacy policy

What we can't tell you, sources and corrections

This isn't financial advice. Figures come from the sources listed, on the dates shown, and they change.

Sources

  1. 10Projects project records: 63 projects in Taloja and 78 in Kharghar, with the middle and lowest starting price in each, read 28 October 2026. 10projects.ai, checked 28 Oct 2026.
  2. Line 1 (Navi Mumbai Metro): 11.1 km and 11 stations from CBD Belapur to Pendhar opened 17 November 2023, the station list in order, fares ₹10 to ₹30 end to end, and the status of each later phase - Wikipedia. en.wikipedia.org, checked 28 Oct 2026.
  3. Maharashtra Cabinet approves ₹5,575 crore Navi Mumbai Metro expansion linking key nodes with NMIA: Line 1A of 3.02 km and Line 2 to the airport, with construction expected to commence in FY 2027-28 and full-scale operations targeted by FY 2031-32 - Free Press Journal, 12 June 2026. www.freepressjournal.in, checked 21 Oct 2026.
  4. Navi Mumbai Metro Line 2, connecting Taloja and Khandeshwar, gets state approval after 15 years: the 8.15 km corridor, its eight named stations, the 2011 proposal at ₹1,605 crore now costed at ₹5,575 crore, and the 2.2 km gap to Pendhar still awaiting approval - Mumbai Live, 21 October 2026. www.mumbailive.com, checked 21 Oct 2026.
  5. Navi Mumbai Metro Line 1 crosses 1.15 crore ridership in two years: trains every 10 minutes at peak and 15 off-peak, fares ₹10 to ₹30 - Free Press Journal, 17 November 2025. www.freepressjournal.in, checked 21 Oct 2026.
  6. Navi Mumbai Metro information, route maps, tenders and updates: no civil contractor for the Taloja MIDC to Khandeshwar line; the only award listed is geotechnical investigation for Line-2 and Line-3 (Zed Geotech Pvt. Ltd.), and tender NMDD-01 for the Detailed Design Consultant for Line-2, Line-3 and Khandeshwar Depot shows as cancelled - The Metro Rail Guy. themetrorailguy.com, checked 28 Oct 2026.
  7. Navi Mumbai Metro route, stations, cost and updates: operational since 17 November 2023, service roughly 06:00 to 22:00, ridership over 12,000 a day - Metro Rail News, page updated 15 September 2026. metrorailnews.in, checked 21 Oct 2026.
  8. Navi Mumbai International Airport: inaugurated 8 October 2025, commercial operations from 25 December 2025, and its metro connections described as approved but not operational - Wikipedia. en.wikipedia.org, checked 21 Oct 2026.
  9. CBD Belapur railway station: served by the Harbour, Trans-Harbour and Port lines, with the Navi Mumbai Metro terminal built adjacent to it - Wikipedia. en.wikipedia.org, checked 21 Oct 2026.
  10. Navi Mumbai Metro Line 1: CIDCO cuts the Belapur to Pendhar run to 25 minutes and 30 seconds, a saving of 90 seconds, under a revised schedule effective 13 July 2026 - Free Press Journal, 10 July 2026. www.freepressjournal.in, checked 21 Oct 2026.
  11. Orange Line (Mumbai Metro), Line 12: Kalyan railway station to Amandoot at Taloja, 22.17 km and 18 stations, listed as under construction since March 2020 with a planned opening of December 2027, and an interchange with the Navi Mumbai Metro at Amandoot - Wikipedia. en.wikipedia.org, checked 28 Oct 2026.
  12. Maharashtra Cabinet approves ₹13,856 crore Metro Line 12A from Manpada-Katai Naka to Taloja: the 18.40 km elevated corridor approved on 27 October 2026, its 12 stations, a cost of ₹13,856.37 crore, an integrated 6.93 km four-lane and 8.69 km six-lane flyover, a projected 4.74 lakh daily riders, MMRDA as the implementing agency, interchanges at Katai Naka with Line 12 and at Amandoot with the Navi Mumbai Metro, and the Chief Minister's three-and-a-half-year deadline - Free Press Journal, 27 October 2026. www.freepressjournal.in, checked 28 Oct 2026.
  13. MMRDA announces the Mumbai Metro Line 12 extension at ₹8,414.53 crore: the 18.4 km Metro 12A corridor from Manpada (Kalyan) to Taloja, its 12 elevated stations named in order, and the alignment running from Kalyan Phata via Dahisar Mori to merge with the existing Line 12 near Khutari village before reaching Taloja railway station, also known as Amandoot - Metro Rail News. metrorailnews.in, checked 28 Oct 2026.
  14. Kalyan-Taloja Metro Line 12 crosses its 100th U-girder; the entire project targeted for completion by May 2028 (Free Press Journal). www.freepressjournal.in, checked 12 Dec 2025.

Corrections

  • 4 Nov 2026: Metro Line 12's target updated from December 2027 to May 2028, as a December 2025 report stated.

Read next

Choose a city or area

    Talk to an advisor

    Add email

    WhatsApp first, one call · Number never sold · Privacy policy

    Your shortlist

    Saved · view shortlist
    Hi! I'm Pooja. Looking at Taloja?